Reconstruction of cardboard production

Description
Created objects: cardboard machines (CBM), thermoelectric power station (TEP), semi-cellulose production plant Amount of investment: 10 891.7 million rubles Source of funding: - own funds: 5 125.2 million rubles; - borrowed funds: 5 766.5 million rubles Stages and terms of project implementation: - 2009-2016 - CBM-1 modernization - 2008-2018 – CBM-2 modernization - 2008-2017 – construction of the flow for NSSC boiling - 2011-2019 - TEP-2 reconstruction Annual tax revenues (planed): 645.0 million rubles Creation of new jobs
Project budget, in million rubles
10891.7
Initiator
Arkhangelsk Pulp and Paper Mill, joint stock company
Priority investment project
Yes
Volume of investments, ₽
over 3000 millions
Industry
Timber industry
Stage of implementation
Implementation phase
Municipal entity
Novodvinsk
ID
249793979
Name
Reconstruction of cardboard production